2020 Pathway Improvement project

Overview


In 2020, the City will be rehabilitating and constructing over a mile of various pathways across the City.

The project includes the following segments:

  • Langton Lake Park – New 8’ bituminous pathway along the north side of the park to create a 7-looped trail. 
  • Central Park – New 8’ bituminous pathway over the existing aglime pathway near the Legion 9 Ballfield. 
  • Tamarack Park – New 8’ bituminous pathway from the playground out to Western Avenue.
  • Resurface pathway on the west side of Willow Pond in Willow Pond Park.
  • Resurface two pathways in Central Park from the Victoria Ballfields to Dale Street.
  • Construct a new 200 foot sidewalk connection on the east side of Dale Street from the B-Dale  parking lot to the existing sidewalk that connects to County Road B sidewalks.
All of these segments are outlined on the Pathway Map.

Schedule


Week of July 13th


  • July 16 – Restoration work on Dale Street sidewalk
  • July 16-17 – Removals on Acorn Park east parking lot
  • July 17 - Restoration work on Legion ballfield pathway; begin concrete work on Acorn Park east parking lot; bituminous patching on Dale Street; removals at BDale Club driveway (2nd half of driveway)

Week of July 20th


  • July 20 – Finish concrete work on Acorn Park east parking lot; concrete work on Dale Street (curbing of 2nd half of BDale Club’s driveway)
  • July 22 – Milling of Langton Lake parking lot
  • July 23 -  Milling of Acorn Park east parking lot
  • July 24 – Pave Acorn Park east parking lot

Week of July 27th

 
  • July 27 – Pave Langton Lake parking lot; striping Acorn Park east parking lot
  • July 28 – Striping Langton Lake parking lot
Schedule is subject to change due to weather.

The project will be completed by October of 2020.